Action Date | Action Description |
---|---|
Monitoring Report | |
Jul 29, 2019 | Assent Application Received |
Jul 29, 2019 | Administrative Review for Completeness |
Jul 30, 2019 | Team Review for Completeness |
Jul 30, 2019 | Team Review for Completeness |
Jul 30, 2019 | Application Accepted |
Jul 31, 2019 | Policy Review |
Aug 01, 2019 | Typist for Processing |
Aug 01, 2019 | Executive Sign Off |
Aug 01, 2019 | Sent to Photo Copy |
Aug 01, 2019 | Permit Approved |
Aug 16, 2019 | HPHC Historical Preservation No Effect |
Feb 24, 2020 | Land Evidence Date |
Mar 05, 2021 | Commencement of Work Notice received |
Dec 07, 2021 | Phone Call |
Dec 09, 2021 | Monitoring Report |
Jul 01, 2022 | Extension of Permit Request |
Jul 27, 2022 | Extension Approved |