Action Date | Action Description |
---|---|
Monitoring Report | |
Sep 12, 2019 | Assent Application Received |
Sep 13, 2019 | Administrative Review for Completeness |
Sep 16, 2019 | Team Review for Completeness |
Sep 16, 2019 | Application Accepted |
Oct 04, 2019 | HPHC Review Pending |
Oct 04, 2019 | Joint Public Notice |
Oct 04, 2019 | HPHC Historical Preservation No Effect |
Nov 04, 2019 | Public Notice End Date |
Nov 07, 2019 | Plans Received |
Nov 08, 2019 | Mail Agenda Notice |
Nov 13, 2019 | Additional Information Received |
Nov 14, 2019 | Geologist Report |
Nov 18, 2019 | Correspondence Mailed/Faxed/E-mailed |
Nov 26, 2019 | Semi-Monthly Meeting Date Scheduled |
Dec 06, 2019 | Typist for Processing |
Dec 06, 2019 | Executive Sign Off |
Dec 06, 2019 | Sent to Photo Copy |
Dec 06, 2019 | Permit Approved |
Dec 13, 2019 | Land Evidence Date |
Jan 17, 2020 | US Army Corps of Engineers Approval Received |
Jan 23, 2020 | Assent Amended |
Jan 26, 2021 | Monitoring Report |
Apr 27, 2022 | Modification Request |
Apr 29, 2022 | Administrative Review for Completeness |
May 02, 2022 | Bio Team Review for Completeness |
May 11, 2022 | HPHC Review Pending |
May 11, 2022 | HPHC Historical Preservation No Effect |
Jun 13, 2022 | Biologist Report |
Jun 14, 2022 | Typist for Processing |
Jun 14, 2022 | Executive Sign Off |
Jun 14, 2022 | Sent to Photo Copy |
Jun 14, 2022 | Permit Mailed |
Jun 14, 2022 | Modification Approved |