Action Date | Action Description |
---|---|
Sep 20, 2019 | Assent Application Received |
Sep 20, 2019 | Administrative Review for Completeness |
Oct 01, 2019 | Team Review for Completeness |
Oct 01, 2019 | Application Accepted |
Oct 16, 2019 | HPHC Review Pending |
Oct 16, 2019 | HPHC Historical Preservation No Effect |
Nov 22, 2019 | Additional Information Requested from Applicant |
Dec 13, 2019 | Biologist Report |
Dec 19, 2019 | Typist for Processing |
Dec 19, 2019 | Executive Sign Off |
Dec 19, 2019 | Sent to Photo Copy |
Dec 19, 2019 | Permit Approved |
Jan 27, 2020 | Land Evidence Date |
Dec 14, 2022 | Extension of Permit Request |
May 08, 2023 | Enforcement Compliance Inspection Required |
May 11, 2023 | Process Extension |
May 11, 2023 | Extension Approved |
Dec 05, 2023 | Extension of Permit Request |
May 17, 2024 | Enforcement Compliance Inspection Required |
May 17, 2024 | Process Extension |
May 17, 2024 | Extension Approved |