Action Date | Action Description |
---|---|
Nov 26, 2019 | Aquaculture Application Received |
Dec 12, 2019 | Aquaculture Administrative Review |
Dec 16, 2019 | Application Accepted |
Dec 16, 2019 | Category B assigned |
Jan 07, 2020 | HPHC Historical Preservation No Effect |
Jan 07, 2020 | HPHC Review Pending |
Jan 27, 2020 | 30 day Public Notice Issued |
Jan 28, 2020 | Objections/Comments Received |
Feb 10, 2020 | Comments Received |
Feb 10, 2020 | Comments Received |
Feb 11, 2020 | Comments Received |
Feb 26, 2020 | Public Notice End Date |
Feb 28, 2020 | Comments Received |
Apr 29, 2020 | Additional Information Received |
Jun 12, 2020 | Comments Received |
Jul 09, 2020 | Mail Agenda Notice |
Jul 10, 2020 | Aquaculture Report |
Jul 28, 2020 | Semi-Monthly Meeting Date Scheduled |
Jul 28, 2020 | Council Approval Granted |
Oct 27, 2020 | Legal Response/Decision |
Oct 27, 2020 | 30 Day Appeal Notification to Owner |
Dec 08, 2020 | Permit Approved |
Dec 09, 2020 | Typist for Processing |
Dec 09, 2020 | Stipulation Package from Aquaculture Coordinator |
Dec 18, 2020 | Aquaculture Lease Mailed |
Dec 24, 2020 | Aquaculture Lease Payment |
Jan 05, 2021 | US Army Corps of Engineers Approval Received |
Jan 11, 2021 | Aquaculture Bond Received |
Jan 11, 2021 | Aquaculture Lease Received |
Dec 28, 2021 | Aquaculture Lease Cover Letter sent |
Jan 18, 2022 | Aquaculture Yearly Questionnaire |
Jan 18, 2022 | Aquaculture Lease Payment |
Dec 17, 2022 | Aquaculture Lease Payment |
Dec 17, 2022 | Aquaculture Yearly Questionnaire |
Dec 28, 2023 | Aquaculture Yearly Questionnaire |
Dec 28, 2023 | Aquaculture Lease Payment |
Dec 31, 2026 | Aquaculture Lease Agreement Expiration Date |