Action Date | Action Description |
---|---|
Feb 18, 2020 | Assent Application Received |
Feb 18, 2020 | Administrative Review for Completeness |
Feb 26, 2020 | Eng Team Review for Completeness |
Feb 26, 2020 | Application Accepted |
Mar 06, 2020 | Project Manager |
Mar 17, 2020 | Typist for Processing |
Mar 17, 2020 | Executive Sign Off |
Mar 17, 2020 | Sent to Photo Copy |
Mar 17, 2020 | Permit Approved |
Mar 17, 2020 | Engineering Report |
Apr 13, 2020 | Land Evidence Date |
May 15, 2020 | HPHC Historical Preservation Comments/Concerns |
May 15, 2020 | HPHC Review Pending |
Dec 28, 2020 | Modification Request |
Dec 30, 2020 | Administrative Review for Completeness |
Jan 08, 2021 | Eng Team Review for Completeness |
Jan 21, 2021 | Engineering Report |
Jan 21, 2021 | Stipulation Package by Engineer |
Jan 21, 2021 | CHA -- application modified due to CHA info |
Jan 21, 2021 | Modification Approved |
Jan 21, 2021 | Typist for Processing |
Jan 21, 2021 | Executive Sign Off |
Jan 21, 2021 | Sent to Photo Copy |
Jan 21, 2021 | HPHC Historical Preservation No Effect |
Jan 21, 2021 | HPHC Review Pending |
Jan 28, 2021 | Land Evidence Date |