Action Date | Action Description |
---|---|
Oct 01, 2021 | Assent Application Received |
Oct 12, 2021 | Administrative Review for Completeness |
Oct 12, 2021 | CHA Worksheet received |
Oct 13, 2021 | Additional Information Requested from Applicant |
Oct 18, 2021 | Plans Received |
Oct 25, 2021 | Plans Received |
Oct 28, 2021 | Application Accepted |
Oct 28, 2021 | Bio Team Review for Completeness |
Nov 02, 2021 | Project Manager |
Nov 30, 2021 | HPHC Review Pending |
Nov 30, 2021 | HPHC Historical Preservation No Effect |
Dec 20, 2021 | Correspondence Mailed/Faxed/E-mailed |
Dec 23, 2021 | Correspondence Received |
Dec 23, 2021 | Biologist Report |
Dec 28, 2021 | Typist for Processing |
Dec 28, 2021 | Permit Approved |
Jan 04, 2022 | Executive Sign Off |
Jan 05, 2022 | Permit Mailed |
Jan 19, 2022 | Land Evidence Date |
Nov 14, 2022 | Commencement of Work Notice received |