Action Date | Action Description |
---|---|
Jan 25, 2022 | Assent Application Received |
Jan 28, 2022 | Administrative Review for Completeness |
Feb 02, 2022 | Bio Team Review for Completeness |
Feb 02, 2022 | Deficient Application - Owner Notification Sent |
Feb 21, 2023 | Deficiency Response Received |
Feb 24, 2023 | Bio Team Review for Completeness |
Feb 24, 2023 | Application Accepted |
Feb 24, 2023 | Project Manager |
Mar 24, 2023 | HPHC Historical Preservation No Effect |
Jun 07, 2023 | Plans Received |
Jun 21, 2023 | Biologist Report |
Jun 22, 2023 | Typist for Processing |
Jun 22, 2023 | Executive Sign Off |
Jun 22, 2023 | Sent to Photo Copy |
Jun 22, 2023 | Permit Approved |
Jun 23, 2023 | Permit Mailed |
Jul 03, 2023 | Land Evidence Date |
Jun 14, 2024 | Commencement of Work Notice received |