Action Date | Action Description |
---|---|
HPHC Review Pending | |
Jan 28, 2022 | Assent Application Received |
Feb 01, 2022 | Administrative Review for Completeness |
Feb 03, 2022 | Category A* (Docks) |
Feb 03, 2022 | Bio Team Review for Completeness |
Feb 03, 2022 | Application Accepted |
Feb 03, 2022 | Project Manager |
Feb 04, 2022 | 30 day Public Notice Issued |
Feb 11, 2022 | HPHC Review Pending |
Feb 11, 2022 | HPHC Historical Preservation No Effect |
Mar 04, 2022 | Public Notice End Date |
Jul 06, 2022 | Phone Call |
Aug 04, 2022 | Correspondence Received |
Aug 04, 2022 | Correspondence Mailed/Faxed/E-mailed |
Oct 17, 2022 | Plans Received |
Oct 24, 2022 | 30 day Public Notice Issued |
Nov 24, 2022 | Public Notice End Date |
Jan 25, 2023 | Plans Received |
Jan 25, 2023 | Biologist Report |
Feb 02, 2023 | Typist for Processing |
Feb 02, 2023 | Executive Sign Off |
Feb 02, 2023 | Sent to Photo Copy |
Feb 02, 2023 | Permit Approved |
Feb 06, 2023 | Permit Mailed |
Mar 08, 2023 | Land Evidence Date |
Aug 23, 2023 | Modification Request |
Aug 24, 2023 | Administrative Review for Completeness |
Aug 29, 2023 | Bio Team Review for Completeness |
Aug 29, 2023 | Application Accepted |
Aug 29, 2023 | Project Manager |
Sep 11, 2023 | Biologist Report |
Sep 11, 2023 | Modification Approved |
Sep 27, 2023 | Land Evidence Date |
Mar 07, 2024 | Dock Post-Construction Certification by Engineer received. |