Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jan 28, 2022 | Assent Application Received |
Feb 01, 2022 | Administrative Review for Completeness |
Feb 04, 2022 | Bio Team Review for Completeness |
Feb 04, 2022 | Additional Information Received |
Feb 04, 2022 | Application Accepted |
Feb 04, 2022 | Project Manager |
Feb 07, 2022 | Category A* (Docks) |
Feb 08, 2022 | 30 day Public Notice Issued |
Feb 11, 2022 | HPHC Review Pending |
Feb 11, 2022 | HPHC Historical Preservation No Effect |
Mar 08, 2022 | Objections/Comments Received |
Mar 08, 2022 | Public Notice End Date |
May 03, 2022 | Objection withdrawal received |
Jun 09, 2022 | Dock/1.1.6 Review approval |
Jun 20, 2022 | Typist for Processing |
Jun 20, 2022 | Executive Sign Off |
Jun 20, 2022 | Sent to Photo Copy |
Jun 20, 2022 | Permit Approved |
Jun 20, 2022 | Biologist Report |
Jun 20, 2022 | Permit Mailed |
Jul 21, 2022 | Awaiting Response from applicant |
Aug 01, 2022 | Land Evidence Date |