Jan 21, 2022 | Freshwater Wetland - Preliminary Determination |
Feb 21, 2022 | Administrative Review for Completeness |
Feb 23, 2022 | Bio Team Review for Completeness |
Feb 23, 2022 | Application Accepted |
Feb 24, 2022 | Project Manager |
Mar 02, 2022 | HPHC Review Pending |
Mar 02, 2022 | HPHC Historical Preservation No Effect |
Mar 08, 2022 | Additional Information Requested from Applicant |
Apr 20, 2022 | Additional Information Requested from Applicant |
Apr 27, 2022 | Phone Call |
Apr 28, 2022 | Correspondence Received |
Apr 28, 2022 | Correspondence Mailed/Faxed/E-mailed |
Aug 01, 2022 | Additional Information Received |
Aug 01, 2022 | Additional Information Requested from Applicant |
Aug 04, 2022 | Typist for Processing |
Aug 04, 2022 | Executive Sign Off |
Aug 04, 2022 | Sent to Photo Copy |
Aug 04, 2022 | Permit Approved |
Aug 04, 2022 | Permit Mailed |
Aug 04, 2022 | Biologist Report |
Nov 22, 2022 | Correspondence Received |