Action Date | Action Description |
---|---|
Feb 04, 2022 | Assent Application Received |
Feb 23, 2022 | Administrative Review for Completeness |
Mar 01, 2022 | Eng Team Review for Completeness |
Mar 01, 2022 | Application Accepted |
Mar 01, 2022 | Project Manager |
Mar 09, 2022 | Plans Received |
Mar 11, 2022 | Engineering Report |
Mar 21, 2022 | HPHC Historical Preservation No Effect |
Mar 21, 2022 | HPHC Review Pending |
Mar 30, 2022 | Permit Approved |
Mar 30, 2022 | Typist for Processing |
Mar 30, 2022 | Executive Sign Off |
Mar 30, 2022 | Sent to Photo Copy |
Mar 31, 2022 | Permit Mailed |