Action Date | Action Description |
---|---|
Mar 04, 2022 | Assent Application Received |
Mar 07, 2022 | Administrative Review for Completeness |
Mar 07, 2022 | CHA Worksheet received |
Mar 08, 2022 | Eng Team Review for Completeness |
Mar 08, 2022 | Application Accepted |
Mar 10, 2022 | Project Manager |
Apr 01, 2022 | HPHC Historical Preservation No Effect |
Apr 01, 2022 | HPHC Review Pending |
Apr 07, 2022 | Meeting Held |
Apr 14, 2022 | 30 day Public Notice Issued |
Apr 20, 2022 | Objections/Comments Received |
Apr 21, 2022 | Water Quality Certification |
May 14, 2022 | Public Notice End Date |
May 25, 2022 | Correspondence Received |
Jun 13, 2022 | Mail Agenda Notice |
Jun 13, 2022 | Plans Received |
Jun 30, 2022 | Semi-Monthly Meeting Date Scheduled |
Jul 14, 2022 | Engineering Report |
Jul 14, 2022 | Biologist Report |
Jul 21, 2022 | Typist for Processing |
Jul 21, 2022 | Permit Approved |
Jul 25, 2022 | Permit Mailed |
Aug 12, 2022 | Plans Received |
Aug 18, 2022 | Land Evidence Date |
Aug 25, 2022 | Meeting Held |
Nov 04, 2022 | Modification Request |
Nov 10, 2022 | Administrative Review for Completeness |
Nov 18, 2022 | Eng Team Review for Completeness |
Dec 20, 2022 | HPHC Historical Preservation No Effect |
Dec 27, 2022 | 30 day Public Notice Issued |
Jan 27, 2023 | Public Notice End Date |
Feb 16, 2023 | Typist for Processing |
Feb 16, 2023 | Executive Sign Off |
Feb 16, 2023 | Sent to Photo Copy |
Feb 16, 2023 | Permit Approved |
Feb 16, 2023 | Biologist Report |
Feb 16, 2023 | Engineering Report |
Feb 16, 2023 | Project Manager |
Feb 17, 2023 | Permit Mailed |
Mar 13, 2023 | Land Evidence Date |
Jun 29, 2023 | Modification Request |
Jul 06, 2023 | Administrative Review for Completeness |
Jul 11, 2023 | Eng Team Review for Completeness |
Jul 11, 2023 | Bio Team Review for Completeness |
Jul 11, 2023 | Application Accepted |
Jul 11, 2023 | Project Manager |
Aug 01, 2023 | HPHC Historical Preservation No Effect |
Aug 08, 2023 | Objections/Comments Received |
Sep 15, 2023 | Biologist Report |
Sep 15, 2023 | Engineering Report |
Sep 21, 2023 | Typist for Processing |
Sep 21, 2023 | Executive Sign Off |
Sep 21, 2023 | Sent to Photo Copy |
Sep 21, 2023 | Permit Approved |
Sep 26, 2023 | Modification Approved |
Oct 16, 2023 | US Army Corps of Engineers Approval Received |
Oct 20, 2023 | Correspondence Received |
Oct 26, 2023 | Land Evidence Date |