Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Mar 22, 2022 | Assent Application Received |
Mar 23, 2022 | Administrative Review for Completeness |
Apr 07, 2022 | Note to File |
Apr 12, 2022 | Category A* (Docks) |
Apr 14, 2022 | Note to File |
Apr 14, 2022 | Application Accepted |
Apr 14, 2022 | Project Manager |
Apr 14, 2022 | Bio Team Review for Completeness |
Apr 28, 2022 | HPHC Historical Preservation No Effect |
Jun 21, 2022 | Correspondence Mailed/Faxed/E-mailed |
Jun 27, 2022 | Correspondence Received |
Jun 28, 2022 | Correspondence Received |
Jul 25, 2022 | Correspondence Mailed/Faxed/E-mailed |
Jul 26, 2022 | Plans Received |
Jul 28, 2022 | Additional Information Received |
Jul 28, 2022 | Additional Information Requested from Applicant |
Jul 28, 2022 | Additional Information Received |
Jul 29, 2022 | Plans Received |
Aug 25, 2022 | 30 day Public Notice Issued |
Sep 25, 2022 | Public Notice End Date |
Oct 03, 2022 | Biologist Report |
Oct 07, 2022 | Permit Mailed |
Oct 07, 2022 | Typist for Processing |
Oct 07, 2022 | Executive Sign Off |
Oct 07, 2022 | Sent to Photo Copy |
Oct 07, 2022 | Permit Approved |
Oct 13, 2022 | Permit Mailed |
Jan 27, 2023 | Land Evidence Date |