Action Date | Action Description |
---|---|
Mar 24, 2022 | Buffer Zone Management Application Received |
Apr 01, 2022 | Administrative Review for Completeness |
Apr 07, 2022 | Bio Team Review for Completeness |
Apr 07, 2022 | Application Accepted |
Apr 07, 2022 | Project Manager |
Apr 28, 2022 | HPHC Review Pending |
Apr 28, 2022 | HPHC Historical Preservation No Effect |
May 19, 2022 | Additional Information Requested from Applicant |
May 26, 2022 | Plans Received |
Jun 27, 2022 | Biologist Report |
Jul 05, 2022 | Permit Mailed |
Jul 05, 2022 | Typist for Processing |
Jul 05, 2022 | Executive Sign Off |
Jul 05, 2022 | Sent to Photo Copy |
Jul 05, 2022 | Permit Approved |
Jul 11, 2022 | Land Evidence Date |
Dec 09, 2022 | Monitoring Report |
Oct 16, 2023 | Monitoring Report |