Action Date | Action Description |
---|---|
Apr 04, 2022 | Assent Application Received |
Apr 06, 2022 | Administrative Review for Completeness |
Apr 07, 2022 | Bio Team Review for Completeness |
Apr 07, 2022 | Application Accepted |
Apr 07, 2022 | Project Manager |
Apr 07, 2022 | Category A* (Docks) |
Apr 19, 2022 | 30 day Public Notice Issued |
Apr 20, 2022 | Comments Received |
May 06, 2022 | HPHC Historical Preservation No Effect |
May 19, 2022 | Public Notice End Date |
Jun 09, 2022 | Dock Meeting -- Approval |
Jun 13, 2022 | Biologist Report |
Jun 15, 2022 | Permit Mailed |
Jun 15, 2022 | Typist for Processing |
Jun 15, 2022 | Executive Sign Off |
Jun 15, 2022 | Sent to Photo Copy |
Jun 15, 2022 | Permit Approved |
Jul 08, 2022 | Land Evidence Date |
Jun 07, 2023 | Dock Post-Construction Certification by Engineer received. |