Action Date | Action Description |
---|---|
Apr 11, 2022 | Assent Application Received |
Apr 15, 2022 | Administrative Review for Completeness |
Apr 26, 2022 | Eng Team Review for Completeness |
Apr 26, 2022 | Bio Team Review for Completeness |
Apr 26, 2022 | Application Accepted |
Apr 26, 2022 | Project Manager |
Apr 26, 2022 | Category B assigned |
May 11, 2022 | HPHC Historical Preservation No Effect |
May 11, 2022 | HPHC Review Pending |
Aug 31, 2022 | 30 day Public Notice Issued |
Sep 30, 2022 | Public Notice End Date |
Oct 31, 2022 | Mail Agenda Notice |
Nov 01, 2022 | Plans Received |
Nov 01, 2022 | Executive Signoff of Staff Reports |
Nov 01, 2022 | Biologist Report |
Nov 01, 2022 | Engineering Report |
Nov 09, 2022 | Semi-Monthly Meeting Date Scheduled |
Nov 09, 2022 | Council Approval Granted |
Dec 13, 2022 | Legal Response/Decision |
Dec 14, 2022 | Typist for Processing |
Dec 14, 2022 | Executive Sign Off |
Dec 14, 2022 | Sent to Photo Copy |
Dec 14, 2022 | Permit Approved |
Dec 14, 2022 | Stipulation Package by Engineer |
Dec 15, 2022 | Permit Mailed |