Action Date | Action Description |
---|---|
Apr 11, 2022 | CHA Worksheet received |
Apr 11, 2022 | Assent Application Received |
May 27, 2022 | Administrative Review for Completeness |
Jun 08, 2022 | Bio Team Review for Completeness |
Jun 08, 2022 | Application Accepted |
Jun 13, 2022 | Project Manager |
Jul 07, 2022 | HPHC Historical Preservation No Effect |
Jul 07, 2022 | HPHC Review Pending |
Oct 24, 2022 | Additional Information Received |
Oct 28, 2022 | Typist for Processing |
Oct 28, 2022 | Executive Sign Off |
Oct 28, 2022 | Sent to Photo Copy |
Oct 28, 2022 | Permit Approved |
Oct 28, 2022 | Biologist Report |
Oct 28, 2022 | Permit Mailed |
Nov 09, 2022 | Land Evidence Date |
Jun 16, 2023 | Note to File |
Aug 03, 2023 | Modification Request |
Aug 04, 2023 | Administrative Review for Completeness |
Aug 07, 2023 | Additional Information Received |
Aug 08, 2023 | Bio Team Review for Completeness |
Aug 08, 2023 | Project Manager |
Aug 23, 2023 | Biologist Report |
Aug 25, 2023 | HPHC Historical Preservation No Effect |
Sep 12, 2023 | Typist for Processing |
Sep 12, 2023 | Executive Sign Off |
Sep 12, 2023 | Sent to Photo Copy |
Sep 12, 2023 | Modification Approved |
Sep 18, 2023 | Permit Mailed |
Sep 26, 2023 | Additional Information Received |
Oct 03, 2023 | Land Evidence Date |