Action Date | Action Description |
---|---|
Apr 11, 2022 | CHA Worksheet received |
Apr 11, 2022 | Assent Application Received |
Apr 15, 2022 | Administrative Review for Completeness |
Apr 20, 2022 | Bio Team Review for Completeness |
Apr 20, 2022 | Application Accepted |
Apr 22, 2022 | Project Manager |
May 11, 2022 | HPHC Historical Preservation No Effect |
May 11, 2022 | HPHC Review Pending |
Jul 25, 2022 | Plans Received |
Sep 28, 2022 | Executive Sign Off |
Sep 28, 2022 | Sent to Photo Copy |
Oct 04, 2022 | Plans Received |
Oct 28, 2022 | Typist for Processing |
Oct 28, 2022 | Biologist Report |
Oct 28, 2022 | Permit Approved |
Oct 28, 2022 | Permit Mailed |
Jan 09, 2023 | Land Evidence Date |
Jul 21, 2023 | Assent Requirement |