Action Date | Action Description |
---|---|
Apr 27, 2022 | Preliminary Determination Request (Coastal) |
Apr 29, 2022 | Administrative Review for Completeness |
May 02, 2022 | Bio Team Review for Completeness |
May 02, 2022 | Application Accepted |
May 05, 2022 | Project Manager |
Jun 13, 2022 | HPHC Review Pending |
Jun 13, 2022 | HPHC Historical Preservation No Effect |
Jun 27, 2022 | Additional Information Received |
Oct 20, 2022 | Biologist Report |
Oct 25, 2022 | Permit Mailed |
Oct 25, 2022 | Typist for Processing |
Oct 25, 2022 | Executive Sign Off |
Oct 25, 2022 | Sent to Photo Copy |
Oct 25, 2022 | Permit Approved |
Oct 31, 2022 | Land Evidence Date |