Action Date | Action Description |
---|---|
Apr 27, 2022 | Assent Application Received |
May 04, 2022 | Administrative Review for Completeness |
May 18, 2022 | HPHC Review Pending |
May 18, 2022 | Bio Team Review for Completeness |
May 18, 2022 | Application Accepted |
May 18, 2022 | HPHC Historical Preservation No Effect |
May 19, 2022 | Project Manager |
May 25, 2022 | Additional Information Requested from Applicant |
Jun 02, 2022 | HPHC Historical Preservation No Effect |
Jun 02, 2022 | HPHC Review Pending |
Jun 24, 2022 | Correspondence Mailed/Faxed/E-mailed |
Sep 08, 2022 | Plans Received |
Sep 14, 2022 | Correspondence Mailed/Faxed/E-mailed |
Sep 16, 2022 | Plans Received |
Oct 06, 2022 | Biologist Report |
Oct 17, 2022 | Engineering Report |
Oct 20, 2022 | Typist for Processing |
Oct 20, 2022 | Executive Sign Off |
Oct 20, 2022 | Sent to Photo Copy |
Oct 20, 2022 | Permit Approved |
Oct 20, 2022 | Permit Mailed |
Nov 08, 2022 | Land Evidence Date |