Action Date | Action Description |
---|---|
May 10, 2022 | Assent Application Received |
May 10, 2022 | Administrative Review for Completeness |
May 17, 2022 | Additional Information Requested from Applicant |
May 23, 2022 | Plans Received |
May 26, 2022 | Application Accepted |
May 26, 2022 | Bio Team Review for Completeness |
Jun 01, 2022 | Project Manager |
Jun 06, 2022 | Permit Approved |
Jun 06, 2022 | Permit Mailed |
Jun 07, 2022 | Additional Information Requested from Applicant |
Jun 07, 2022 | Correspondence Received |
Jun 07, 2022 | Correspondence Mailed/Faxed/E-mailed |
Jun 09, 2022 | Additional Information Received |
Jun 09, 2022 | Typist for Processing |
Jun 09, 2022 | Executive Sign Off |
Jun 09, 2022 | Sent to Photo Copy |
Jun 09, 2022 | Biologist Report |
Jun 09, 2022 | Permit Approved |
Jun 09, 2022 | Permit Mailed |
Jun 17, 2022 | Duplicate Original Assent requested/mailed |
Jun 20, 2022 | HPHC Historical Preservation No Effect |
Jun 20, 2022 | HPHC Review Pending |
Jan 10, 2023 | Land Evidence Date |