Action Date | Action Description |
---|---|
May 11, 2022 | Maintenance Certification Request |
May 31, 2022 | Additional Information Received |
Jun 01, 2022 | Administrative Review for Completeness |
Jun 06, 2022 | Eng Team Review for Completeness |
Jun 06, 2022 | Deficient Application - Owner Notification Sent |
Nov 16, 2022 | Deficiency Response Received |
Dec 01, 2022 | Eng Team Review for Completeness |
Dec 01, 2022 | Application Accepted |
Dec 13, 2022 | HPHC Historical Preservation No Effect |
Jan 10, 2023 | 30 day Public Notice Issued |
Feb 10, 2023 | Public Notice End Date |
Feb 27, 2023 | Engineering Report |
Mar 07, 2023 | Typist for Processing |
Mar 07, 2023 | Executive Sign Off |
Mar 07, 2023 | Sent to Photo Copy |
Mar 07, 2023 | Permit Approved |
Mar 09, 2023 | Permit Mailed |
Apr 05, 2023 | Land Evidence Date |
Apr 14, 2023 | Commencement of Work Notice received |
Jun 30, 2023 | Dock Post-Construction Certification by Engineer received. |