Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
May 26, 2022 | Assent Application Received |
May 31, 2022 | Administrative Review for Completeness |
Jun 01, 2022 | Bio Team Review for Completeness |
Jun 01, 2022 | Application Accepted |
Jun 06, 2022 | Project Manager |
Jun 06, 2022 | Category A* (Docks) |
Jun 13, 2022 | HPHC Review Pending |
Jun 13, 2022 | HPHC Historical Preservation No Effect |
Jun 14, 2022 | Additional Information Received |
Sep 27, 2022 | 30 day Public Notice Issued |
Oct 05, 2022 | US Army Corps of Engineers Approval Received |
Oct 27, 2022 | Public Notice End Date |
Nov 17, 2022 | Biologist Report |
Nov 30, 2022 | Typist for Processing |
Nov 30, 2022 | Executive Sign Off |
Nov 30, 2022 | Sent to Photo Copy |
Nov 30, 2022 | Permit Approved |
Dec 01, 2022 | Permit Mailed |
Dec 23, 2022 | Land Evidence Date |