Action Date | Action Description |
---|---|
May 27, 2022 | CHA Worksheet received |
May 27, 2022 | Assent Application Received |
Jun 03, 2022 | Administrative Review for Completeness |
Jun 20, 2022 | Bio Team Review for Completeness |
Jun 21, 2022 | Deficient Application - Owner Notification Sent |
Jul 12, 2022 | Deficient Application Picked Up |
Sep 06, 2022 | Deficiency Response Received |
Sep 15, 2022 | Bio Team Review for Completeness |
Sep 15, 2022 | Application Accepted |
Sep 20, 2022 | Project Manager |
Oct 26, 2022 | HPHC Historical Preservation Comments/Concerns |
Dec 01, 2022 | HPHC Historical Preservation No Effect |
Dec 01, 2022 | Biologist Report |
Dec 05, 2022 | Typist for Processing |
Dec 05, 2022 | Executive Sign Off |
Dec 05, 2022 | Sent to Photo Copy |
Dec 05, 2022 | Permit Approved |
Dec 07, 2022 | Permit Mailed |
Dec 20, 2022 | Land Evidence Date |
Jun 15, 2023 | Commencement of Work Notice received |