Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
May 27, 2022 | Assent Application Received |
Jun 03, 2022 | Administrative Review for Completeness |
Jun 07, 2022 | Category A* (Docks) |
Jun 07, 2022 | Bio Team Review for Completeness |
Jun 07, 2022 | Application Accepted |
Jun 10, 2022 | Project Manager |
Jun 13, 2022 | Additional Information Requested from Applicant |
Jun 21, 2022 | HPHC Historical Preservation No Effect |
Jun 21, 2022 | HPHC Review Pending |
Jul 12, 2022 | Additional Information Requested from Applicant |
Jul 12, 2022 | Additional Information Received |
Jul 18, 2022 | 30 day Public Notice Issued |
Aug 17, 2022 | Dock Meeting -- Approval |
Aug 18, 2022 | Public Notice End Date |
Aug 18, 2022 | Biologist Report |
Aug 26, 2022 | Typist for Processing |
Aug 26, 2022 | Executive Sign Off |
Aug 26, 2022 | Sent to Photo Copy |
Aug 26, 2022 | Permit Approved |
Aug 26, 2022 | Permit Mailed |
Sep 16, 2022 | Land Evidence Date |