Action Date | Action Description |
---|---|
Jun 03, 2022 | Assent Application Received |
Jul 21, 2022 | Administrative Review for Completeness |
Jul 21, 2022 | Deficient Application - Owner Notification Sent |
Aug 03, 2022 | Deficient Application Picked Up |
Sep 07, 2022 | Deficiency Response Received |
Sep 12, 2022 | Bio Team Review for Completeness |
Sep 12, 2022 | Application Accepted |
Sep 13, 2022 | Project Manager |
Oct 07, 2022 | HPHC Historical Preservation No Effect |
Oct 27, 2022 | Additional Information Received |
Oct 28, 2022 | Biologist Report |
Nov 01, 2022 | Typist for Processing |
Nov 01, 2022 | Executive Sign Off |
Nov 01, 2022 | Sent to Photo Copy |
Nov 01, 2022 | Permit Approved |
Nov 01, 2022 | Permit Mailed |
Nov 14, 2022 | Land Evidence Date |