Action Date | Action Description |
---|---|
Jun 10, 2022 | Assent Application Received |
Jun 15, 2022 | Administrative Review for Completeness |
Jun 24, 2022 | Bio Team Review for Completeness |
Jun 27, 2022 | Deficient Application - Owner Notification Sent |
Jul 01, 2022 | Deficient Application Picked Up |
Jul 12, 2022 | Deficiency Response Received |
Jul 21, 2022 | Bio Team Review for Completeness |
Jul 21, 2022 | Application Accepted |
Jul 21, 2022 | Project Manager |
Aug 02, 2022 | HPHC Historical Preservation No Effect |
Sep 23, 2022 | Additional Information Requested from Applicant |
Nov 23, 2022 | Biologist Report |
Nov 30, 2022 | Typist for Processing |
Nov 30, 2022 | Executive Sign Off |
Nov 30, 2022 | Sent to Photo Copy |
Nov 30, 2022 | Permit Approved |
Dec 02, 2022 | Permit Mailed |
Jan 19, 2023 | Land Evidence Date |