Jun 22, 2022 | Assent Application Received |
Jun 27, 2022 | Administrative Review for Completeness |
Jun 29, 2022 | Bio Team Review for Completeness |
Jun 29, 2022 | Application Accepted |
Jul 01, 2022 | Project Manager |
Aug 15, 2022 | Additional Information Received |
Aug 15, 2022 | HPHC Historical Preservation No Effect |
Aug 25, 2022 | Correspondence Mailed/Faxed/E-mailed |
Sep 28, 2022 | Plans Received |
Oct 19, 2022 | Comments Received |
Oct 19, 2022 | Objections/Comments Received |
Oct 25, 2022 | Objections/Comments Received |
Oct 26, 2022 | Entry of Appearance Received |
Oct 26, 2022 | Objections/Comments Received |
Oct 26, 2022 | Public Notice End Date |
Oct 28, 2022 | Additional Information Received |
Nov 01, 2022 | Correspondence Mailed/Faxed/E-mailed |
Nov 01, 2022 | 30 day Public Notice Issued |
Nov 14, 2022 | Objections/Comments Received |
Nov 18, 2022 | Objections/Comments Received |
Nov 21, 2022 | Objections/Comments Received |
Dec 01, 2022 | Public Notice End Date |
Dec 06, 2022 | Additional Information Requested from Applicant |
Dec 14, 2022 | Correspondence Mailed/Faxed/E-mailed |
Dec 28, 2022 | Additional Information Received |
Feb 08, 2023 | Engineering Report |
Feb 08, 2023 | Biologist Report |
Feb 14, 2023 | Mail Agenda Notice |
Feb 21, 2023 | Executive Signoff of Staff Reports |
Feb 28, 2023 | Semi-Monthly Meeting Date Scheduled |
Feb 28, 2023 | Council Approval Granted |
Jun 27, 2023 | Legal Response/Decision |
Jul 17, 2023 | Stipulation Package from Biologist |
Jul 20, 2023 | Stipulation Package by Engineer |
Jul 27, 2023 | Typist for Processing |
Jul 27, 2023 | Executive Sign Off |
Jul 27, 2023 | Sent to Photo Copy |
Jul 27, 2023 | Permit Approved |
Jul 27, 2023 | Permit Mailed |
Mar 08, 2024 | Commencement of Work Notice received |