Action Date | Action Description |
---|---|
Jul 01, 2022 | Maintenance Certification Request |
Jul 07, 2022 | Administrative Review for Completeness |
Jul 12, 2022 | Eng Team Review for Completeness |
Jul 19, 2022 | Deficient Application - Owner Notification Sent |
Jul 22, 2022 | Deficient Application Picked Up |
Feb 15, 2023 | Deficiency Response Received |
Feb 23, 2023 | Eng Team Review for Completeness |
Feb 23, 2023 | Application Accepted |
Feb 23, 2023 | Project Manager |
Mar 15, 2023 | HPHC Historical Preservation No Effect |
Aug 22, 2023 | Engineering Report |
Aug 24, 2023 | Typist for Processing |
Aug 24, 2023 | Executive Sign Off |
Aug 24, 2023 | Sent to Photo Copy |
Aug 24, 2023 | Permit Approved |
Aug 29, 2023 | Permit Mailed |
Sep 27, 2023 | Land Evidence Date |
Oct 15, 2024 | Commencement of Work Notice received |