Action Date | Action Description |
---|---|
Jul 26, 2022 | Assent Application Received |
Aug 02, 2022 | Administrative Review for Completeness |
Aug 05, 2022 | Bio Team Review for Completeness |
Aug 05, 2022 | Application Accepted |
Aug 09, 2022 | Project Manager |
Aug 12, 2022 | HPHC Historical Preservation No Effect |
Aug 22, 2022 | Biologist Report |
Aug 25, 2022 | Typist for Processing |
Aug 25, 2022 | Executive Sign Off |
Aug 25, 2022 | Sent to Photo Copy |
Aug 25, 2022 | Permit Approved |
Aug 25, 2022 | Permit Mailed |