Action Date | Action Description |
---|---|
Jul 25, 2022 | Assent Application Received |
Aug 03, 2022 | Administrative Review for Completeness |
Aug 04, 2022 | Eng Team Review for Completeness |
Aug 04, 2022 | Application Accepted |
Aug 15, 2022 | Project Manager |
Sep 12, 2022 | Engineering Report |
Sep 16, 2022 | Typist for Processing |
Sep 16, 2022 | Executive Sign Off |
Sep 16, 2022 | Sent to Photo Copy |
Sep 16, 2022 | Permit Approved |
Sep 16, 2022 | Permit Mailed |
Sep 23, 2022 | HPHC Historical Preservation No Effect |