Action Date | Action Description |
---|---|
Aug 02, 2022 | Assent Application Received |
Aug 05, 2022 | Administrative Review for Completeness |
Aug 05, 2022 | Bio Team Review for Completeness |
Aug 05, 2022 | Application Accepted |
Aug 09, 2022 | Project Manager |
Aug 12, 2022 | HPHC Historical Preservation No Effect |
Jun 23, 2023 | Biologist Report |
Jun 26, 2023 | Plans Received |
Jun 28, 2023 | Typist for Processing |
Jun 28, 2023 | Executive Sign Off |
Jun 28, 2023 | Sent to Photo Copy |
Jun 28, 2023 | Permit Approved |
Jun 30, 2023 | Permit Mailed |
Aug 07, 2023 | Land Evidence Date |