Action Date | Action Description |
---|---|
Aug 02, 2022 | CHA Worksheet received |
Aug 02, 2022 | Assent Application Received |
Aug 04, 2022 | Administrative Review for Completeness |
Sep 08, 2022 | Bio Team Review for Completeness |
Sep 08, 2022 | Application Accepted |
Sep 20, 2022 | Project Manager |
Sep 30, 2022 | Additional Information Received |
Oct 26, 2022 | HPHC Historical Preservation Comments/Concerns |
Nov 29, 2022 | HPHC Historical Preservation No Effect |
Jan 11, 2023 | Biologist Report |
Jan 11, 2023 | Engineering Report |
Jan 17, 2023 | Typist for Processing |
Jan 17, 2023 | Executive Sign Off |
Jan 17, 2023 | Sent to Photo Copy |
Jan 17, 2023 | Permit Approved |
Jan 19, 2023 | Permit Mailed |
Feb 22, 2023 | Duplicate Original Assent requested/mailed |
Oct 05, 2023 | Land Evidence Date |