Action Date | Action Description |
---|---|
Aug 03, 2022 | CHA Worksheet received |
Aug 03, 2022 | Assent Application Received |
Aug 05, 2022 | Administrative Review for Completeness |
Sep 30, 2022 | Eng Team Review for Completeness |
Sep 30, 2022 | Application Accepted |
Sep 30, 2022 | Project Manager |
Oct 17, 2022 | Engineering Report |
Oct 17, 2022 | Typist for Processing |
Oct 17, 2022 | Executive Sign Off |
Oct 17, 2022 | Sent to Photo Copy |
Oct 17, 2022 | Permit Approved |
Oct 17, 2022 | Permit Mailed |
Oct 18, 2022 | HPHC Historical Preservation No Effect |
Nov 23, 2022 | Land Evidence Date |