Action Date | Action Description |
---|---|
Biologist Report | |
Aug 04, 2022 | Assent Application Received |
Aug 11, 2022 | Administrative Review for Completeness |
Aug 18, 2022 | Bio Team Review for Completeness |
Aug 18, 2022 | Deficient Application - Owner Notification Sent |
Aug 25, 2022 | Deficient Application Picked Up |
Aug 29, 2022 | Deficiency Response Received |
Sep 01, 2022 | Bio Team Review for Completeness |
Sep 01, 2022 | Application Accepted |
Sep 06, 2022 | Project Manager |
Sep 06, 2022 | Category A* (Docks) |
Sep 23, 2022 | HPHC Historical Preservation No Effect |
Sep 27, 2022 | 30 day Public Notice Issued |
Oct 05, 2022 | US Army Corps of Engineers Approval Received |
Oct 27, 2022 | Public Notice End Date |
Dec 14, 2022 | Correspondence Mailed/Faxed/E-mailed |
Oct 16, 2023 | 30-Day Notification of Cancellation letter |
Feb 09, 2024 | Application Cancelled |