Action Date | Action Description |
---|---|
Aug 24, 2022 | CHA Worksheet received |
Aug 24, 2022 | Assent Application Received |
Aug 25, 2022 | Administrative Review for Completeness |
Sep 01, 2022 | Bio Team Review for Completeness |
Sep 06, 2022 | Deficient Application - Owner Notification Sent |
Sep 16, 2022 | Deficient Application Picked Up |
Oct 12, 2022 | Deficiency Response Received |
Oct 21, 2022 | Bio Team Review for Completeness |
Oct 21, 2022 | Application Accepted |
Oct 24, 2022 | Project Manager |
Nov 25, 2022 | HPHC Historical Preservation No Effect |
Dec 16, 2022 | Additional Information Received |
Jan 19, 2023 | Additional Information Received |
Jan 24, 2023 | Biologist Report |
Feb 09, 2023 | Typist for Processing |
Feb 09, 2023 | Executive Sign Off |
Feb 09, 2023 | Sent to Photo Copy |
Feb 09, 2023 | Permit Approved |
Feb 13, 2023 | Permit Mailed |
Feb 20, 2023 | Land Evidence Date |