Action Date | Action Description |
---|---|
Assent Requirement | |
Sep 08, 2022 | Assent Application Received |
Sep 13, 2022 | Administrative Review for Completeness |
Sep 15, 2022 | Bio Team Review for Completeness |
Sep 15, 2022 | Application Accepted |
Sep 20, 2022 | Project Manager |
Oct 03, 2022 | Plans Received |
Oct 04, 2022 | HPHC Historical Preservation No Effect |
Oct 28, 2022 | Plans Received |
Oct 31, 2022 | Biologist Report |
Nov 02, 2022 | Typist for Processing |
Nov 02, 2022 | Executive Sign Off |
Nov 02, 2022 | Sent to Photo Copy |
Nov 02, 2022 | Permit Approved |
Nov 02, 2022 | Permit Mailed |
Jan 27, 2023 | Commencement of Work Notice received |
Feb 23, 2023 | Land Evidence Date |