Action Date | Action Description |
---|---|
Sep 14, 2022 | Assent Application Received |
Sep 19, 2022 | Administrative Review for Completeness |
Sep 23, 2022 | Eng Team Review for Completeness |
Sep 23, 2022 | Application Accepted |
Sep 26, 2022 | Project Manager |
Sep 30, 2022 | HPHC Historical Preservation No Effect |
Oct 13, 2022 | Additional Information Requested from Applicant |
Dec 08, 2022 | Plans Received |
Jan 04, 2023 | 30 day Public Notice Issued |
Jan 12, 2023 | Letter of Support for Project |
Jan 19, 2023 | Dock/1.1.6 Review approval |
Jan 20, 2023 | Letter of Support for Project |
Jan 30, 2023 | Correspondence Received |
Feb 04, 2023 | Public Notice End Date |
Feb 06, 2023 | Objections/Comments Received |
Feb 20, 2023 | Objection withdrawal received |
Feb 20, 2023 | Typist for Processing |
Feb 20, 2023 | Executive Sign Off |
Feb 20, 2023 | Sent to Photo Copy |
Feb 20, 2023 | Permit Approved |
Feb 20, 2023 | Engineering Report |
Feb 27, 2023 | Permit Mailed |
Oct 07, 2024 | Duplicate Original Assent requested/mailed |
Oct 17, 2024 | Land Evidence Date |