Action Date | Action Description |
---|---|
Sep 12, 2022 | Assent Application Received |
Sep 16, 2022 | Additional Information Received |
Sep 21, 2022 | Bio Team Review for Completeness |
Sep 21, 2022 | Application Accepted |
Sep 21, 2022 | Administrative Review for Completeness |
Sep 26, 2022 | Project Manager |
Oct 18, 2022 | HPHC Historical Preservation No Effect |
Dec 01, 2022 | Biologist Report |
Dec 12, 2022 | Typist for Processing |
Dec 12, 2022 | Executive Sign Off |
Dec 12, 2022 | Sent to Photo Copy |
Dec 12, 2022 | Permit Approved |
Dec 14, 2022 | Permit Mailed |