Action Date | Action Description |
---|---|
Sep 27, 2022 | Assent Application Received |
Sep 30, 2022 | Administrative Review for Completeness |
Oct 17, 2022 | Bio Team Review for Completeness |
Oct 17, 2022 | Application Accepted |
Oct 24, 2022 | Project Manager |
Dec 06, 2022 | HPHC Historical Preservation Comments/Concerns |
Dec 07, 2022 | HPHC Historical Preservation No Effect |
Dec 19, 2022 | Additional Information Received |
Mar 24, 2023 | Additional Information Received |
May 03, 2023 | Additional Information Received |
May 15, 2023 | Engineering Report |
Jun 06, 2023 | Typist for Processing |
Jun 06, 2023 | Executive Sign Off |
Jun 06, 2023 | Sent to Photo Copy |
Jun 06, 2023 | Permit Approved |
Jun 08, 2023 | Permit Mailed |
Jun 29, 2023 | Land Evidence Date |
Jul 05, 2023 | Commencement of Work Notice received |