Action Date | Action Description |
---|---|
Oct 12, 2022 | Assent Application Received |
Oct 18, 2022 | Administrative Review for Completeness |
Oct 21, 2022 | Bio Team Review for Completeness |
Oct 21, 2022 | Application Accepted |
Oct 21, 2022 | Category A* (Docks) |
Oct 24, 2022 | 30 day Public Notice Issued |
Oct 24, 2022 | Project Manager |
Nov 24, 2022 | Public Notice End Date |
Nov 25, 2022 | HPHC Historical Preservation No Effect |
Dec 08, 2022 | Biologist Report |
Dec 13, 2022 | Permit Approved |
Dec 13, 2022 | Typist for Processing |
Dec 13, 2022 | Executive Sign Off |
Dec 13, 2022 | Sent to Photo Copy |
Dec 15, 2022 | Permit Mailed |
Jan 17, 2023 | Land Evidence Date |
Jun 10, 2024 | Commencement of Work Notice received |
Sep 13, 2024 | Dock Post-Construction Certification by Engineer received. |