Action Date | Action Description |
---|---|
Oct 03, 2022 | Maintenance Certification Request |
Oct 20, 2022 | Additional Information Received |
Oct 21, 2022 | Administrative Review for Completeness |
Oct 31, 2022 | Engineering Report |
Nov 09, 2022 | Deficient Application - Owner Notification Sent |
Nov 22, 2022 | Deficient Application Picked Up |
Jan 23, 2023 | Deficiency Response Received |
Feb 07, 2023 | Eng Team Review for Completeness |
Feb 07, 2023 | Application Accepted |
Feb 07, 2023 | Permit Approved |
Feb 08, 2023 | Permit Mailed |