Action Date | Action Description |
---|---|
Oct 20, 2022 | Assent Application Received |
Jan 03, 2023 | Administrative Review for Completeness |
Jan 04, 2023 | Project Manager |
Jan 04, 2023 | Application Accepted |
Jan 05, 2023 | Bio Team Review for Completeness |
Jan 17, 2023 | Additional Information Received |
Jan 17, 2023 | HPHC Historical Preservation No Effect |
May 18, 2023 | Additional Information Received |
Jun 20, 2023 | Plans Received |
Jun 11, 2024 | Biologist Report |
Jun 18, 2024 | Typist for Processing |
Jun 18, 2024 | Executive Sign Off |
Jun 18, 2024 | Sent to Photo Copy |
Jun 18, 2024 | Permit Approved |
Jun 21, 2024 | Permit Mailed |
Sep 09, 2024 | Duplicate Original Assent requested/mailed |
Oct 18, 2024 | Land Evidence Date |