Action Date | Action Description |
---|---|
Oct 26, 2022 | Maintenance Certification Request |
Nov 02, 2022 | Administrative Review for Completeness |
Nov 18, 2022 | Eng Team Review for Completeness |
Nov 18, 2022 | Additional Information Requested from Applicant |
Dec 09, 2022 | Additional Information Received |
Dec 20, 2022 | Eng Team Review for Completeness |
Jan 10, 2023 | Deficient Application - Owner Notification Sent |
May 01, 2023 | Deficiency Response Received |
May 23, 2023 | Bio Team Review for Completeness |
May 23, 2023 | Eng Team Review for Completeness |
Jun 01, 2023 | Application Accepted |
Jun 05, 2023 | Engineering Report |
Jun 05, 2023 | Typist for Processing |
Jun 05, 2023 | Executive Sign Off |
Jun 05, 2023 | Sent to Photo Copy |
Jun 05, 2023 | Permit Approved |
Jun 06, 2023 | Permit Mailed |
Jun 14, 2023 | HPHC Historical Preservation No Effect |
Oct 03, 2023 | Land Evidence Date |