Action Date | Action Description |
---|---|
Nov 15, 2022 | Maintenance Certification Request |
Nov 21, 2022 | Administrative Review for Completeness |
Nov 21, 2022 | Bio Team Review for Completeness |
Nov 21, 2022 | Application Accepted |
Nov 21, 2022 | Project Manager |
Nov 21, 2022 | Category A assigned |
Dec 20, 2022 | HPHC Historical Preservation No Effect |
Jan 11, 2023 | Biologist Report |
Jan 17, 2023 | Typist for Processing |
Jan 17, 2023 | Executive Sign Off |
Jan 17, 2023 | Sent to Photo Copy |
Jan 17, 2023 | Permit Approved |
Jan 19, 2023 | Permit Mailed |
Feb 22, 2023 | Land Evidence Date |
Mar 24, 2023 | Additional Information Received |