Action Date | Action Description |
---|---|
Jan 30, 2023 | Assent Application Received |
Feb 01, 2023 | Administrative Review for Completeness |
Feb 16, 2023 | Bio Team Review for Completeness |
Feb 16, 2023 | Application Accepted |
Feb 16, 2023 | Project Manager |
Feb 28, 2023 | HPHC Historical Preservation No Effect |
Mar 16, 2023 | Biologist Report |
Mar 24, 2023 | Typist for Processing |
Mar 24, 2023 | Executive Sign Off |
Mar 24, 2023 | Sent to Photo Copy |
Mar 24, 2023 | Permit Approved |
Mar 30, 2023 | Permit Mailed |