Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Feb 08, 2023 | Assent Application Received |
Feb 14, 2023 | Administrative Review for Completeness |
Feb 16, 2023 | Bio Team Review for Completeness |
Feb 16, 2023 | Application Accepted |
Feb 17, 2023 | Project Manager |
Feb 17, 2023 | Category A* (Docks) |
Feb 28, 2023 | HPHC Historical Preservation No Effect |
Apr 07, 2023 | Additional Information Received |
Apr 07, 2023 | Additional Information Received |
Apr 12, 2023 | Correspondence Mailed/Faxed/E-mailed |
Apr 12, 2023 | Comments Received |
Apr 25, 2023 | Correspondence Received |
Jun 21, 2023 | 30 day Public Notice Issued |
Jul 03, 2023 | Letter of Support for Project |
Jul 21, 2023 | Public Notice End Date |
Oct 04, 2023 | Additional Information Requested from Applicant |
Oct 19, 2023 | Biologist Report |
Oct 20, 2023 | Typist for Processing |
Oct 20, 2023 | Executive Sign Off |
Oct 20, 2023 | Sent to Photo Copy |
Oct 20, 2023 | Permit Approved |
Oct 24, 2023 | Permit Mailed |
Nov 10, 2023 | Land Evidence Date |