Action Date | Action Description |
---|---|
Mar 13, 2023 | Assent Application Received |
Mar 17, 2023 | Administrative Review for Completeness |
Mar 31, 2023 | Eng Team Review for Completeness |
Mar 31, 2023 | Bio Team Review for Completeness |
Mar 31, 2023 | Application Accepted |
Mar 31, 2023 | Project Manager |
Apr 11, 2023 | HPHC Historical Preservation No Effect |
May 10, 2023 | Biologist Report |
May 10, 2023 | Engineering Report |
May 17, 2023 | Typist for Processing |
May 17, 2023 | Executive Sign Off |
May 17, 2023 | Sent to Photo Copy |
May 17, 2023 | Permit Approved |
May 19, 2023 | Permit Mailed |
Jun 13, 2023 | Correspondence Received |