Action Date | Action Description |
---|---|
Mar 29, 2023 | CHA Worksheet received |
Mar 29, 2023 | Assent Application Received |
Apr 04, 2023 | Administrative Review for Completeness |
Apr 12, 2023 | Bio Team Review for Completeness |
Apr 12, 2023 | Application Accepted |
Apr 12, 2023 | Project Manager |
Apr 19, 2023 | HPHC Historical Preservation No Effect |
May 08, 2023 | Biologist Report |
May 10, 2023 | Additional Information Received |
May 11, 2023 | 30 day Public Notice Issued |
Jun 10, 2023 | Public Notice End Date |
Jun 27, 2023 | Engineering Report |
Jun 29, 2023 | Typist for Processing |
Jun 29, 2023 | Executive Sign Off |
Jun 29, 2023 | Sent to Photo Copy |
Jun 29, 2023 | Permit Approved |
Jul 07, 2023 | Permit Mailed |