Action Date | Action Description |
---|---|
Mar 31, 2023 | Assent Application Received |
Apr 07, 2023 | Administrative Review for Completeness |
Apr 13, 2023 | Bio Team Review for Completeness |
Apr 13, 2023 | Application Accepted |
Apr 13, 2023 | Project Manager |
Apr 19, 2023 | HPHC Historical Preservation No Effect |
May 08, 2023 | Additional Information Requested from Applicant |
May 16, 2023 | Additional Information Received |
Jul 10, 2023 | Additional Information Requested from Applicant |
Jul 12, 2023 | Biologist Report |
Jul 13, 2023 | Typist for Processing |
Jul 13, 2023 | Executive Sign Off |
Jul 13, 2023 | Sent to Photo Copy |
Jul 13, 2023 | Permit Approved |
Jul 17, 2023 | Permit Mailed |
Jul 21, 2023 | Land Evidence Date |